Monthly Updates Archives - Glenham Mills

Monthly Updates

All the posts published.
Below is a summary of activities during the last month related to the former Texaco Beacon Research Facility. Environmental Update The semi-annual groundwater monitoring event that was discussed in last month’s update has been completed.  On a concurrent track, we continue to work on the draft Feasibility Studies that are the next major deliverable to [...]
Below is a summary of activities during the last month related to the former Texaco Beacon Research Facility. Environmental Update In late April, groundwater samples were collected on site as part of the semi-annual groundwater sampling event required by the Consent Order. These results are shared with the New York State Department of Environmental Conservation [...]
Below is a summary of activities during the last month related to the former Texaco Beacon Research Facility. Environmental Update We continue to work on preparing the draft Feasibility Studies (FS) for the site, which are the next major deliverable to the New York State Department of Environmental Conservation. The first FS will cover the [...]
There are no additional environmental or real estate updates since our January post, which can be found here.
Below is a summary of activities during the last month related to the former Texaco Beacon Research Facility. Environmental Update The revised Remedial Investigation Report (RIR) incorporating comments from the New York State Department of Environmental Conservation (NYSDEC) has been submitted to the agency.  We are focusing on the preparation of Feasibility Studies for the [...]
There are no environmental or real estate updates since our November post. We will continue to provide regular updates in 2021. Happy New Year!
Below is a summary of activities during the last month related to the former Texaco Beacon Research Facility. Environmental Update We have submitted a proposed schedule to the New York State Department of Environmental Conservation for the Feasibility Study. Real Estate Update Our environmental assessments have progressed nicely and we are starting to re-engage various [...]
Environmental Update We are revising the draft Remedial Investigation Report (RIR) to incorporate comments from the New York State Department of Environmental Conservation (NYSDEC) for submittal in early November. Once the agency accepts the RIR, the next step will be to begin working on the Feasibility Study. Real Estate Update There is no real estate [...]
Below is a summary of activities during the last month related to the former Texaco Beacon Research Facility. Environmental Update We received draft comments from the New York State Department of Environmental Conservation (NYSDEC) on the Remedial Investigation Report. The next step is NYSDEC acceptance of the report, which may occur within the coming months. [...]
Below is a summary of activities during the last month related to the former Texaco Beacon Research Facility. Environmental Update The Remedial Investigation Report is under review by the New York State Department of Environmental Conservation and the New York State Department of Health.  Chevron expects to receive comments following agency reviews. Real Estate Update [...]